Andheri Gokhale-Barfiwala Bridge Connection to be Completed Within a Month - Municipal Update

user Admin
  • 28th May 2024
  • 1264
  • 0
Andheri Gokhale-Barfiwala Bridge Connection to be Completed Within a Month - Municipal Update
Never miss any update
Join our WhatsApp Channel

The Gopalakrishna Gokhale Bridge, connecting Andheri East and West, is progressing rapidly and is scheduled to be completed by June 30, 2024. The work to link this bridge to the C.D. Barfiwala Flyover is underway, adhering to the set timeline. Municipal officials, along with technical advisors from Veermata Jijabai Technological Institute (VJTI), are closely monitoring the project.

Elevation and Integration of Barfiwala Flyover

The process to elevate and connect the Barfiwala Flyover to the newly constructed Gokhale Bridge began on April 14, 2024. The methodology and plan for raising the Barfiwala Flyover were designed by IIT and VJTI. VJTI developed the procedure, and IIT reviewed it, suggesting improvements. The implementation of this revised method is being carried out under VJTI's supervision.

Methodology for Bridge Integration

The final two girders of the Barfiwala Flyover, P9 to P10 and P10 to P11, need to be separated. This involves controlled RCC joint demolition at pillars PA and P10, ensuring no structural damage.

Girders P9 to P10 and P10 to P11 will be lifted using a synchronized system to match the level of the Gokhale Bridge. Once aligned, the joints will be concreted again to ensure stability. New bearings and connecting joints will be installed.

Progress of the Integration Work

The level of the Barfiwala Flyover at pillar P10 was proposed to be raised by approximately 750 mm. This adjustment has been completed. At pillar P11, the proposed level raise was approximately 1,350 mm. Around 1,250 mm of this has been achieved, with the remaining 100 mm expected to be aligned within the next two to three days.

The new bearings have been procured and tested on May 27, and will be brought to the project site immediately.

Remaining work, including RCC concreting at P9, P10, and P11, and installation of new bearings, is scheduled to be completed by June 5. The project will conclude after the concrete curing process.


Related Topics / Tags

Admin

Author

Admin

...


Comments

Add Comment

No comments yet.

Add Your Comment

Relevant Blogs

Infrastructure
Pimpri Chinchwad Leads Maharashtra's War on Pollution with GRAP Rollout

Maharashtra’s First Anti-Pollution Action Plan Unveiled The Pimpri Chinchwad Municipal Corporation (PCMC) has implemented the Graded Response Ac

Infrastructure
Goa's Infrastructure Revolution is a Boost for Real Estate Growth

Goa's infrastructure transformation is not just elevating the state’s engineering standards but is also reshaping its real estate landscape. Wit

Infrastructure
Introducing High-Tech Solutions For Mumbai Parking Problems

Mumbai is addressing its severe parking challenges with robotic multilevel parking and expanded on-street parking options. A 14-story robotic parking