Andheri Gokhale-Barfiwala Bridge Connection to be Completed Within a Month - Municipal Update

user Admin
  • 28th May 2024
  • 1221
  • 0
Andheri Gokhale-Barfiwala Bridge Connection to be Completed Within a Month - Municipal Update
Never miss any update
Join our WhatsApp Channel

The Gopalakrishna Gokhale Bridge, connecting Andheri East and West, is progressing rapidly and is scheduled to be completed by June 30, 2024. The work to link this bridge to the C.D. Barfiwala Flyover is underway, adhering to the set timeline. Municipal officials, along with technical advisors from Veermata Jijabai Technological Institute (VJTI), are closely monitoring the project.

Elevation and Integration of Barfiwala Flyover

The process to elevate and connect the Barfiwala Flyover to the newly constructed Gokhale Bridge began on April 14, 2024. The methodology and plan for raising the Barfiwala Flyover were designed by IIT and VJTI. VJTI developed the procedure, and IIT reviewed it, suggesting improvements. The implementation of this revised method is being carried out under VJTI's supervision.

Methodology for Bridge Integration

The final two girders of the Barfiwala Flyover, P9 to P10 and P10 to P11, need to be separated. This involves controlled RCC joint demolition at pillars PA and P10, ensuring no structural damage.

Girders P9 to P10 and P10 to P11 will be lifted using a synchronized system to match the level of the Gokhale Bridge. Once aligned, the joints will be concreted again to ensure stability. New bearings and connecting joints will be installed.

Progress of the Integration Work

The level of the Barfiwala Flyover at pillar P10 was proposed to be raised by approximately 750 mm. This adjustment has been completed. At pillar P11, the proposed level raise was approximately 1,350 mm. Around 1,250 mm of this has been achieved, with the remaining 100 mm expected to be aligned within the next two to three days.

The new bearings have been procured and tested on May 27, and will be brought to the project site immediately.

Remaining work, including RCC concreting at P9, P10, and P11, and installation of new bearings, is scheduled to be completed by June 5. The project will conclude after the concrete curing process.


Related Topics / Tags

Admin

Author

Admin

...


Comments

Add Comment

No comments yet.

Add Your Comment

Relevant Blogs

Infrastructure
Boisar Bullet Train Station - Enhancing Connectivity and Economic Growth !!

Palghar, Maharashtra: The construction of a modern station for the Mumbai-Ahmedabad bullet train in Boisar, Palghar district, is expected to signific

Infrastructure
Mumbai Coastal Road Arch Bridge Set for Partial Opening on September 15, 2024

BMC Plans Limited Opening of Coastal Road Arch Bridge Mumbai: The BMC has indicated that one arm of the Mumbai Coastal Road arch bridge, connected t

Infrastructure
Indian Railway Ministry Approves Survey for New Nashik-Dahanu Rail Line to Enhance Connectivity and Boost Tourism

The Indian Railway Ministry has reportedly given the green light for the final location survey of a new 100-kilometer rail line that will connect Nash